Campus Renewal Construction Updates: Oct. 13

Friday, October 13, 2017

As visitors to campus may have noticed, accessing the library and French classroom still requires going around the back of the building. The work has taken longer than expected, and with the recent wet weather the work and the temporary access will take another week at least. The contractors are creating trench drains and spreading the sub-base material ahead of installation of asphalt pavers in the area. We apologize for any inconvenience.

We're happy to share that we've achieved a big construction milestone this week: power is now on in the Arts & Community Center building! This allows workers to test and begin using the mechanical equipment inside.